 Active Construction Projects Last updated Sept. 2, 2010
|
Latest Updates |
Up-coming Construction |
|
CH 16 : Savage |
Overlays : Countywide |
|
What Roads are Closed? |
|
CH 8 - From CH 15 to TH 21 CH 12 – Prior Lake CH 16 – At Glendale & Lynn in Savage CH 66 - From CH 59 to CH 61 (Begins Aug 23rd) CH 86 – From TH 19 to CH 27 |
|
|
COUNTY HIGHWAY 8 SAND CREEK TWP., MN & HELENA TWP., MN |
| |
|
Location |
This project is located on CH 8, just west of Xanadu Ave. in the Townships of Sand Creek & Helena.
 |
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
County Inspector |
Paul Holmboe |
952-496-8052 |
|
Contractor |
S.M. Hentges |
952-492-5700 |
| |
|
Documents |
|
|
|
|
|
|
|
| |
|
Status |
This project is in progress.
S.M. Hentges is the bridge contractor and is currently working on the grading to the new bridge approaches. Completed pile driving and now working on footings and abutments. CH 8 will remain closed and detoured between CH 15 and TH 21 until the completion of the new bridge. The completion date has not been established.
Back to the top of the page |
|

|
COUNTY HIGHWAY 12 PRIOR LAKE, MN |
| |
|
Location |
This project is located on CH 12, from 1.05 miles east of CH 17 to 0.38 miles west of TH 13 in City of Prior Lake.
 |
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
County Inspector |
Dan Swanson |
952-496-8479 |
|
City Engineer |
Larry Poppler |
952-447-9832 |
|
Contractor |
Chard Tiling & Excavation |
612-328-1153 [Emergency] |
| |
|
Documents |
Newsletter No. 1 |
Newsletter No. 2 |
|
|
|
|
|
|
| Message from the City of Prior Lake |
Chard Tiling is installing two 2" above ground temporary water lines on Spring Lk Rd from Monroe Ave to Lime Rd. The two lines are fed off of the hydrant at Monroe Ave & Spring Lk Rd. The temporary lines will allow them to provide water service to homes while they remove and replace underground utilities in the street. 3020, 3040, 3050, and 3070 Creekview Cir, 2958, 2972, 2977, 2986, 2987, 3003, 3013, 3019, 3031, 3044, 3051, 3063, 3068, 3091, 3111, 3124, 3133, 3141, 3144, and 3160 Spring Lk Rd and 16991 and 16994 Monroe will be serviced off of the two 2" temporary water lines. Once the lines have been filled with water and tested, representatives from Chard Tiling will begin working with the residents to make the switch over to the 2"temporary water lines.
Chard anticipates making the temporary water switch over on Friday 8/27 and beginning the underground utility work on Monday 8/30.one at this time.
|
|
|
|
Status |
This project is in progress.
CH 12 is closed to thru traffic. Please adhere to posted detours as indicated in the map above.
The road build for CH 12 from the West end to Northwoods is awaiting the curb crew. City utility work is expected to start from Monroe to Lime St. on Aug. 30th. On the east end, work will continue behind the curbs, this will require construction equipment and vehicles to be active on the sides of the road, please use caution and watch for workers. The completion date is September 2, 2011. Back to the top of the page |
|

|
COUNTY HIGHWAY 16 – ROUNDABOUT SAVAGE, MN |
| |
|
Location |
This project is located on CH 16, at the intersection of Lynn Avenue and Glendale Road in City of Savage.

|
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
County Inspector |
Dan Swanson |
952-496-8479 |
|
Contractor |
Northwest Asphalt |
|
| |
|
Documents |
Detour Map |
|
|
|
|
|
|
| |
|
Status |
This project is in progress.
This intersection is closed to all traffic until the afternoon of September 3rd.
The sub layers of Asphalt have been placed and trails and walks are being paved.
Sept. 2 - Final paving.
Sept. 3 - Striping, then open to traffic.
Work will continue on site after Sept. 3rd so please be aware of construction vehicles and personnel.
A full closure of the intersection will remain for the duration of the project.
The completion date is September, 2010. Back to the top of the page |
|

|
COUNTY HIGHWAY 18 PRIOR LAKE & SHAKOPEE, MN |
| |
|
Location |
This project is located on CH 18 from CH 42 to Crossings Blvd. in Cities of Prior Lake and Shakopee.

|
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
County Inspector |
Paul Holmboe |
952-496-8052 |
|
Contractor |
Northwest Asphalt |
|
| |
|
Documents |
Newsletter No. 1 |
Newsletter No. 2 |
|
|
|
|
|
| |
|
Status |
This project is substantially complete.
This project is substantially completed and is open for traffic. Only minor work and repairs are being performed. Please be aware of construction vehicles and equipment.
Back to the top of the page |
|

|
COUNTY HIGHWAY 21 SHAKOPEE, MN |
| |
|
Location |
This project is located on County Highway 21 from County Highway 42 to Trunk Highway 169 in the City of Shakopee. |
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
Construction Inspector |
Mike Fashant |
952-496-8051 |
|
Contractor |
Enebak Construction |
507-645-8962 |
| |
|
Documents |
11 x 17 Lay-out Map |
Handout Map |
|
|
|
|
|
| |
|
Status |
This project is in progress.
The contractor is installing storm sewer between CR 42 and CR 16. Work is also being performed on the bus ramp at the entrance to TH 169. Southbridge Parkway/Pike Lake Road has been re-opened.
The completion date is July 20, 2012. Back to the top of the page |
|

|
COUNTY HIGHWAY 66 JORDAN, MN |
| |
|
Location |
This project is located on County Highway 66 from County Highway 59 to County Highway 61 in the City of Jordan. |
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
Construction Inspector |
|
|
|
Contractor |
Chard Tiling & Excavation |
612-328-1153 [Emergency] |
| |
|
Documents |
|
|
|
|
|
|
|
| |
|
Status |
This project is in progress.
Beginning Aug 23rd CH 66 will close between CH 59 and CH 61 for a box culvert replacement. This road will remain closed until mid – Oct. Please follow the posted detour.
The completion date is December, 2010. Back to the top of the page |
|

|
COUNTY HIGHWAY 83 SHAKOPEE, MN |
| |
|
Location |
This project is located on County Highway 83 from County Highway 42 to County Highway 16 in the City of Shakopee.

|
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
Construction Inspector |
Mike Fashant |
952-496-8051 |
|
Contractor |
S.M. Hentges |
952-492-5700 [Emergency] |
| |
|
Documents |
Newsletter No. 1 |
Newsletter No. 2 |
|
|
|
|
|
| |
|
Status |
This project is substantially complete.
This project is substantially completed and is open for traffic. Only minor work and repairs are being performed. Please be aware of construction vehicles and equipment.
Work is expected to be complete in late summer, 2010. Back to the top of the page |
|

|
COUNTY HIGHWAY 86 TRUNK HIGHWAY 19 SCOTT COUNTY, MN |
| |
|
Location |
This project runs along the Scott and Rice County borders. Construction will be from the intersection of County Highway 27 to the Trunk Highway 19 connection.

|
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
Inspector |
Dan Swanson |
952-496-8479 |
|
Contractor |
Friedges |
612-685-7327 |
| |
|
Documents |
Newsletter No. 1 |
Newsletter No. 2 |
|
|
|
|
|
| |
|
Status |
This project is in progress.
County Highway 86 is Closed from the new TH 19 Roundabout to CH 27 (Texas Avenue) to thru traffic; only local traffic is permitted. Rice County Highway 96 at Scott County Highway 86 is closed as well to thru traffic.
Paving operations are in progress and should last for the next week. Please use caution navigating this area.
All construction is expected to be completed in September 2010. Back to the top of the page |
|

|
2010 BITUMINOUS OVERLAYS SCOTT COUNTY, MN |
| |
|
Location |
CH 8 from CH 15 to TH 21 (Helena Twp) - COMPLETE CH 23 from CH 8 to Village Lake Drive (Prior Lake) - In Progress CH 42 from CH 27 to Glendale Road (Savage) - Start Sept 20th, Night Work CH 64 from CH 15 to CH 89 (Helena Twp) - COMPLETE |
| |
|
Contacts |
Construction Manager |
Len Laxen |
952-496-8097 |
|
Construction Inspector |
Paul Holmboe |
952-496-8052 |
|
Contractor |
Valley Paving |
|
| |
|
Documents |
MAP |
|
|
|
|
|
|
| |
|
Status |
This project is in progress.
Valley Paving has completed the bituminous overlays on CH 8 and CH 64. Shouldering and lane markings should be completed by the end of July. CH 23 and CH 42 overlays are scheduled to be paved in late August. Due to the volume of traffic on CH 42, that overlay will begin Monday Aug 23rd, at night between the hours of 8:00 pm and 6:00 am. The completion date is not available at this time. Back to the top of the page |
|
|