None. Work is complete.
Starting June 10th, a temporary creek bypass will be put in to replace the existing bridge with three box culverts.
June 15, 2020: Tree clearing is underway. Creek diversion and bridge removal to begin next week.
June 30, 2020: Box culverts were installed and back filled. Road work and paving will begin and road is on schedule to be reopened to the public in a few weeks.
July 23, 2020: CH 15 bridge is now open. Crews will continue to work on the roadway to complete shoulder and striping work. No further road closures are expected.